Exam Code | SMC |
Exam Name | Scrum Master Certified (SMC) |
Questions | 147 Questions Answers With Explanation |
Update Date | October 20,2024 |
Price |
Was : |
Prepare Yourself Expertly for SMC Exam:
Our team of highly skilled and experienced professionals is dedicated to delivering up-to-date and precise study materials in PDF format to our customers. We deeply value both your time and financial investment, and we have spared no effort to provide you with the highest quality work. We ensure that our students consistently achieve a score of more than 95% in the Scrum SMC exam. You provide only authentic and reliable study material. Our team of professionals is always working very keenly to keep the material updated. Hence, they communicate to the students quickly if there is any change in the SMC dumps file. The Scrum SMC exam question answers and SMC dumps we offer are as genuine as studying the actual exam content.
You can reach out to our agents at any time for guidance; we are available 24/7. Our agent will provide you information you need; you can ask them any questions you have. We are here to provide you with a complete study material file you need to pass your SMC exam with extraordinary marks.
Pass4surexams provide trusted study material. If you want to meet a sweeping success in your exam you must sign up for the complete preparation at Pass4surexams and we will provide you with such genuine material that will help you succeed with distinction. Our experts work tirelessly for our customers, ensuring a seamless journey to passing the Scrum SMC exam on the first attempt. We have already helped a lot of students to ace IT certification exams with our genuine SMC Exam Question Answers. Don't wait and join us today to collect your favorite certification exam study material and get your dream job quickly.
Enroll with confidence at Pass4surexams, and not only will you access our comprehensive Scrum SMC exam question answers and dumps, but you will also benefit from a remarkable offer – 90 days of free updates. In the dynamic landscape of certification exams, our commitment to your success doesn't waver. If there are any changes or updates to the Scrum SMC exam content during the 90-day period, rest assured that our team will promptly notify you and provide the latest study materials, ensuring you are thoroughly prepared for success in your exam."
Quality is the heart of our service that's why we offer our students real exam questions with 100% passing assurance in the first attempt. Our SMC dumps PDF have been carved by the experienced experts exactly on the model of real exam question answers in which you are going to appear to get your certification.
The Chief Scrum Master plays an important role during the Retrospect Project process. By being a part of the Retrospect Project Meeting, he/she provides valuable inputs mainly to identify, document, and internalize the lessons learned during the process. What is an output of this process?
A. Agreed Actionable Improvements.
B. Agreed Actionable Schedule.
C. Agreed Actionable Lessons.
D. Agreed Actionable Objectives.
The senior management of a multi-national company undertakes turnkey projects. To provide better value to customers, the senior management wants to implement Scrum in the organization. Which of the following is NOT a Scrum principle that can be used as a selling point to illustrate the benefits of Scrum to customers?
A. Self-organization.
B. Collaboration.
C. Value-based Prioritization.
D. Theoretical process control.
The Chief Scrum Master facilitates the Scrum of Scrums Meeting. Which of the following statements about a Scrum of Scrums Meeting is true?
A. This meeting can be conducted at any time without any pre-determined intervals.
B. This meeting can be scaled up.
C. This meeting is always time-boxed.
D. This meeting is relevant only for high-investment projects.
A town has begun a project that involves keeping track of the buses traveling on the roads of the town. Which of the following is NOT a characteristic of this project if it is managed according to Scrum Framework?
A. Detailed upfront planning will be done to ensure that risks are identified early on.
B. The team working on this project will meet every day for 15 minutes to list impediments to completing their tasks.
C. The Product Owner will prioritize the tasks that deliver maximum business value.
D. The customer does not have to be able to define very concrete requirements early on.
All of the following statements about Risk Communications are true, EXCEPT:
A. The Stakeholders should be continuously informed about risks, including the potential impact of these risks and the plans for responding to each risk.
B. The Scrum Team may also discuss specific risks related to their Tasks with the Product Owner duringDaily Standup Meetings.
C. The Product Owner is responsible for the prioritization of risks and for communicating the prioritized list to the Scrum Team.
D. Information related to risks is maintained and updated through the Risk Burndown Chart.